Over the past few weeks, our ARP team has been working on the following:

  • B6 (Old Power Station) demolition is in progress with D7, D8 & D10 structure approximately 60% complete
  • B6 (Old Power Station) D8 & D10 engine removal approximately 50% complete
  • B26 E1-E4 pedestal demolition is 100% complete

Upcoming works for the next 4 weeks are expected to include:

  • Continued demolition of B6 (Old Power Station) building
  • Demolition of B2 Training Centre

When demolition is occurring our neighbours and passersby may notice the following disturbances:

  • Demolition noise from the construction equipment, which will be mitigated by limiting work to daytime production hours only (ie. 7:00am to 4:00pm)
  • Localised airbourne dust, which will be mitigated by mist mechanisms and stockpile covers
  • Increased truck traffic along Cemetery Road to remove building materials and engine components, which will be mitigated by flag men while trucks enter and exit the demolition site.

SAFETY & SIGNAGE
Project safety signage and project barriers are in place surrounding all demolition and work/project areas. All project areas are limited to the BELCO Serpentine Road campus only.

We ask our neighbours, passersby and campus visitors/guests to observe all safety signage and to not enter or attempt to enter any marked project areas in order to protect the safety of everyone.