Over the past few weeks, the project team has been working on the following:
- B5 Warehouse 2 demolition is complete
- B4 GT2 building superstructure and turbine demolition presently well underway
- B26 – EPS diesel engine disassembly nicely underway with E1 to E4 interior ductwork removal complete
- Building cleanout has begun in B2 Training Centre while nearing completion in B6 OPS and B4 GT2
- Interior building cleanout of B6 OPS progressing to completion and also throughout B26 EPS
When demolition is ocurring our neighbours and passersby may notice the following disturbances:
- Demolition noise from the construction equipment, which will be mitigated by limiting work to daytime production hours only (ie. 7:00am to 4:00pm)
- Localised airbourne dust, which will be mitigated by mist mechanisms and stockpile covers
- Increased truck traffic along Cemetery Road to remove building materials and engine components, which will be mitigated by flag men while trucks enter and exit the demolition site.
SAFETY & SIGNAGE
Project safety signage and project barriers are in place surrounding all demolition and work/project areas. All project areas are limited to the BELCO Serpentine Road campus only.
We ask our neighbours, passersby and campus visitors/guests to observe all safety signage and to not enter any marked project areas in order to protect the safety of everyone.